Hardcover relatively rough housing projects more acceptance , acceptance is the main content of the issue of the construction process , we have to pay attention to a few points :

1, before Shou Fang , owners can collect some information about all moved content to targeted when all moved , or the owner may be submitted in advance to participate submitted there together , learn some basic common sense.

2 , the owner can prepare some basic tools , such as : 25g ring drum hammer , tape measure, plumb bob , marker, buckets , electric pen .

3 , to the property should first look at the houses of two books a table , or " residential quality guarantee ", " Residential Manual " and " final acceptance table ."

4 , check the doors and windows wpc laminate flooring price.

The outside of the window to see if there is water dripping along the junction of the frame and the wall is sealed waterproof glue full , complete, in order to prevent rainwater infiltration wall ; Repeat whether to open or close the doors and windows and all components check normal use ; checking whether doors and windows surface were damaged ; checking whether plastic glass full , plump ; verticality doors and windows you can use plumb bob to detect .

5 , hydropower check

Electrical checks, you can open the electricity used to check whether the normal power switches , sockets inspection , we can take a row socket to check to see if the indicator to judge the work normally ; wire diameter can be removed several sockets, wire and quality inspection .

Check the water , open all water equipment , switching back and forth a few times to check the integrity and usability , water basin should be filled with water, and then check the pipe connections for leaks , and check the drainage pipes unobstructed and leakage problems composite board uk suppliers.

6 , tile hollowing inspection

Hammer with a loud drum slide back and forth on the tile surface , determine its voice , the voice was thick sound , accompanied by empty feeling , hollowing application area of ​​more than 15x15cm pen mark out a few numbers .

7 , check the decorative materials

Check the decorative materials mainly to check the flatness of the material of construction, vertical, construction technology, the quality of the paint brush custom decks and fences.

8 storey inspection

Storey scene only indoor space height measurement method + + plaster slab thickness layer thickness = storey height of the interior space can be directly measured with a ruler , do not choose when measured corner should choose the middle position measurement , the state of the plaster layer thickness 5cm, slab thickness can consult property or real estate , are usually designed to : between 0.10 ~ 0.16m, several numerical sum is the actual story .