Content Tip : In general, the decoration of a 140-150 square meter three-bedroom house , from start to finish takes about 45 days . Smaller small apartment with two bedrooms can save four or five days and more than 200 square meters duplex apartment with four need more than five days. How to improve the speed improvements ? Weapon for you to see me help you efficiently complete the renovation event !
Share fitting time schedule , how to improve the decoration speed wood grain terrace border landscaping?
1, the work force ( playing hide works trough, according to the original design have to dismantle the wall , cleaning ) 2-3 days to complete.
2 , plumbers and electricians ( strength wire wiring , water supply and drainage piping ) 3-4 days to complete.
3 , masonry ( based on the need for civil engineering design of the rooms - built walls , doors, windows and other shift , paving tiles , trunking landfill ) 7-25 days to complete. 4 , woodworking ( furniture , decorative walls, doors and windows production ) 15 - 30 days.
5 , painting ( furniture, paint , wall paint ) 20 - 30 days .
6 Other ( wood floor installation , lighting ware and other finished products such as the overall bath room installation and commissioning, wasteland clean ) 4 - 7 days
Masonry work to improve the speed of approach:
1 , together with the required material in place to get ready deck board furniture.
2 , for civil reconstruction more complicated place ( such as arc-shaped wall , etc. ) explained in detail the construction process and on-site supervision of construction , to allow workers to be aware of order to improve the speed and quality of construction and construction.
3 , the purchased material ( in particular tiles ) the geometry must be taken as standard , is again reduced to its processing (e.g., milling correction ) , to ensure the normal construction .
4 , according to the site area , due to increase construction workers .
5 , pay attention to the order of the construction location , usually built wall - hall ( various halls ) - bedroom - kitchen and bathroom - balcony, so as to facilitate other processes ( such as carpentry ) for cross work .
Improve the speed of a carpentry :
1 , together with the required material in place to get ready composite timber garden box.
2 , if you can buy the finished furniture or home manufacturers do, as far as possible off-site production ( such as wardrobes ) , the best is to buy a whole suite door windows ( factory -made ) . This will shorten the construction time.
3, where more complex shapes ( such as decorative walls, etc. ) explained in detail the construction process and on-site supervision of construction workers to be aware of order to improve the speed and quality of construction and construction.
4, note the order of production projects , usually , the hall ceiling - decorative wall - closet - shoe TV cabinet - doors and windows. Position is concerned, the bedroom - living room - balcony - kitchen . Thereby facilitating other processes ( such as painting ) the cross work .
Improving working speed painting method :
1 , together with the required material in place to get ready .
2 , the construction workers for at least two more.
3, due to the work of the painter 's decision , comes into play , other processes are best to have entered the final stage.
4 , increase the indoor air velocity ! Strengthen ventilation with fan, ( especially after bottoming quickly dried ) to quickly dry putty ( which is the most time-consuming step of a painting ) .
5 , pay attention to the order of production projects , usually , furniture, paint - paint the walls .
You have to remind NOTE: custom furniture , etc. should be booked in advance , otherwise it will affect the duration of the work must be coordinated cross in place , otherwise , just the opposite , uh , may be appropriate points of overtime pay and extend working hours to keep track of the daily work ! ! ! schedule, reducing downtime occurrence frequency ! If this renovation , Sanshiliangting double guard room of 100 square meters set time is probably 45 to 60 days .
Keywords: ebay hardwood slats for garden benches suppliers waterproof wood sheet material plastic patio tiles privacy fence vinyl black free pool deck plans for 27 round pool outdoor patio flooring options outside wpc composite coverings flower pots made of composites wrapping wood trim with vinyl 84 lumber cider fence composite black rocking chairs outdoor how deep to make outdoor bench seat vynil porch flooring brick and plastic composite stairs synthetic wood for decks.
没有评论:
发表评论